CBO: NASA needs $24 billion a year to stick to schedules

by | Apr 16, 2009 | Ares, Constellation, exploration, International Space Station, NASA, Space Shuttle | 0 comments

NASA needs to increase its annual average funding by $5 billion to almost $24 billion for the next decade to achieve its 2020 Moon and International Space Station (ISS) goals and be able to fly the Space Shuttles to 2015

The $5 billion prediction is from the NASA authorisation act 2008 mandated US Congressional Budget Office’s (CBO) analysis of NASA’s forecasted budgets and its past programmes’ cost performance. The $5 billion figure is from 50% cost overrun estimates based on a 2004 CBO analysis of 72 past NASA programmes

The CBO also found that with no changes to NASA’s budget to achieve the 2020 Moon and ISS goals would mean cuts to the science and aeronautics budgets

In November 2008 a CBO analysis concluded that Orion-Ares’ costs could spiral by $7 billion and its first manned flight may be two years later than planned in 2017

Thanks to Jeff Foust and his tweet for alerting me to this report

About Seradata

Seradata produces the renowned Seradata database. Trusted by over 100 of the world’s leading Space organisations, Seradata is a fully queryable database used for market analysis, failure/risk assessment, spectrum analysis and space situational awareness (SSA).

For more information go to https://www.seradata.com/product/

Related Articles

Categories

Archives

Tags

nasaspacexecoreviewsissesaArianespacevideochinaFalcon 9v1.2FT Block 525virgin galacticULAfalcon 9evaRoscosmosspacewalkDGAaviation weekBlue OriginInternational Space StationaresIGTsoyuzRocket LabBeidouawardsStarlinkspaceAirbus DSboeingSatellite broadcastingrussiamoonOneWebISROCargo Return VehiclemarsblogresearchspaceshiptwojaxaorionmarsimpactdelayhyperbolaEutelsatdemocratrocketlunarhypertextobamagoogle lunar prizelaunchVegathales alenia spaceSESconstellationtourismbarack obamafiguresnorthspaceflightIntelsatnode 2fundedRaymond Lygo2009Lockheed MartinExpress MD-2Elon MuskAtlas Vromess2dassault aviationaviationLucy2008wk2sstlukradiosuborbitaltestmissiledocking portexplorationAriane 5 ECAVirgin OrbitinternetSLSLong March 2D/2ElectronNorthrop GrummanChina Manned Space Engineeringsts-122Ariane 5missile defensenewspapercotsgalileospace tourismflight2010Long March 4CspaceportExpress AMU 1buildspace stationaltairsoyuz 2-1aProton Minternational astronautical congressshuttlespace shuttleAriane 6scaled compositesIntelsat 23European Space AgencyLauncherOneCosmoshanleybudgetrulesnew yorkatvVietnamshenzhoucongressMojaveboldennew shepardLong March 2CInmarsatOrbital ATKcnesiaclunar landerGuiana Space CenterApollolawsUS Air ForceSpace Systems/LoralUK Space AgencyLong March 4BKuaizhou 1AkscILSprotondarpaTalulah RileyElectron KSFalcon 9v1.2 Block 5Vega CNorth KoreaeuSkylonAstriumpicturebaseusaastronautdragonlanderfiveeventTelesatSSLAprilSNC50thinterviewLong MarchSea LaunchfalconWednesdaycustomerlinkatlantissuccessor

Stay Informed with Seradata

Stay informed on the latest news, insights, and more from Seradata by signing up for our newsletter.